PHYSICAL PLANT UPDATE

March 15, 2004 – March 19, 2004

 

UPDATES/ROAD/PARKING CLOSURESthe following buildings/parking areas will be affected during the coming week:

 

v   The road and parking lot behind Wright Hall will be open Wednesday, March 17, 2004.

 

v     The back road from Dickey Hall to Hansberry Hall continues to be closed to traffic. The projected opening is the end of May.

 

NOTE:  The road continues to be closed to pedestrian traffic also for the week of March 15th through Friday, March 19th.

 

v   The parking area along the road between Dickey Hall and the Physical Plant will be closed Monday, March 15th and Tuesday, March 16th.  The road will be open for traffic.

 

cccccccccccccccccccc

 

INFORMATION UPDATE

 

Ø    The tunnel is progressing between Lucy Laney and Langston Hughes Library.

 

Ø    The new water tower base has been poured and erection of the tower should start in the next week or two.

 

Ø    Timber removal for the new dorm starts Monday, March 15th and should be completed by Tuesday, March 16th.  There will be no parking in the parking area along the road between Dickey Hall and the Physical Plant.

 

Ø    Some restoration has begun around the campus.  We are on the way home!

 

 

 

cccccccccccccccccccc

 

Walt Konopka, Heery International is the Construction Manager for these projects and Gerry Davis is the Project Administrator for Lincoln University. All questions, problems etc. will be addressed through them to the appropriate contractor.  You may contact them through the Office of the Physical Plant at extension 3111.  Your cooperation and understanding are appreciated!  Remember – these are your tax dollars at work!


Lincoln University of the Commonwealth of Pennsylvania
1570 Baltimore Pike, P.O. Box 179, Lincoln University, PA 19352 (484) 365-8000 Internet Privacy Policy